Answer:
1. $20
2. $4,999
Explanation:
1. The computation of plantwide predetermined overhead rate is shown below:-
Predetermined rate = Estimated overheads ÷ Estimated Machine hours + Variable rate per hour
= 4,410,000 ÷ 245,000 + 2
= $20 per machine hour
2. The computation of total manufacturing cost assigned to Job P90 is shown below:-
total manufacturing cost assigned to Job P90 = Direct material + Direct labor + Overhead applied
= $1,886 + $1,353 + (88 × 20)
= $1,886 + $1,353 + 1,760
= $4,999