Answer:
44
Step-by-step explanation:
Calculation for the due date that should be set for this project
First step is Find the square root of 4 which is 2 then we are going to cross multiply 2 by z value of 95% which is 1.645 which gives us 3.29(2×1.645).
Second step is to add the numbers of days which is 40 days to 3.29 which gives us the due date that should be set for this project which is 43.29(40 days + 3.29) approximately 44.
Due date=
1.645 = (x - 40)/√4
1.645=(x - 40) /2
Cross multiplication
1.645×2=(x-40)
x=(1.645×2)+40 days
x=3.29+40 days
x=43.29
Approximately 44 days
Therefore the due date that should be set for this project will be 44 days