Compute the Work-in-Process transferred to the finished goods warehouse on April 30 using the following information:

Work-In-Process Inventory, April 30 $275
Direct material purchased during April 250
Work-In-Process Inventory, April 1 300
Direct labor costs incurred 400
Manufacturing overhead costs 350
Direct materials used in production 225

User Archarius
by
7.9k points

1 Answer

4 votes

Answer:

$1,100

Step-by-step explanation:

Computation for the Work-in-Process transferred to the finished goods warehouse on April 30

Work-In-Process Inventory, April 1 300

Direct materials used in production 225

Direct labor costs incurred 400

Manufacturing overhead costs 350

Less Work-In-Process Inventory, April 30 ($175)

Work-in-Process transferred to the finished goods warehouse $1,100

Therefore the Work-in-Process transferred to the finished goods warehouse on April 30 will be $1,100

User Corpsekicker
by
8.2k points
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.