30.6k views
0 votes
Date

Page
12 workers were employed to complete the
construction of a building in 60 days
How many additional numbers op workers
should be employed to complete constrichon in
45 days?​

User Nirsky
by
6.2k points

1 Answer

5 votes

Answer:

16 workers are required to complete the work in 45 days...

Explanation:

12 workers are required to complete the work in 60 days

so... 60*12=720 workers are required to complete the work in 1 day

Hence,

720/45 = 16 workers are required to complete the work in 45 days.

User Ehsan Ali
by
5.9k points