Answer:
$6.65 per hour
Step-by-step explanation:
We can determine the predetermined overhead rate by
Estimated factory overhead cost / Estimated number of direct labor hours.
Estimated factory overhead cost = $1,530,000
Estimated number of direct labor hours = 230,000 hours
= $1,530,000 / 230,000
= $6.65 per hour
Predetermined overhead rate is $6.65 per hour