The following data have been recorded for recently completed Job 450 on its job cost sheet. Direct materials cost was $2,049. A total of 35 direct labor-hours and 195 machine-hours were worked on the job. The direct labor wage rate is $21 per labor-hour. The Corporation applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $24 per machine-hour. The total cost for the job on its job cost sheet would be:

User Nhrcpt
by
8.3k points

1 Answer

4 votes

Answer:

Total cost= $7,464

Step-by-step explanation:

Giving the following information:

Job 450:

Direct materials= $2,049

35 direct labor-hours

195 machine-hours

The direct labor wage rate is $21 per labor-hour.

The predetermined overhead rate is $24 per machine-hour.

The total cost is calculated using the following formula:

Total cost= direct material + direct labor + allocated overhead

Total cost= 2,049 + 35*21 + 195*24

Total cost= 2,049 + 735 + 4,680

Total cost= $7,464

User Ashton Engberg
by
8.8k points

No related questions found

Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.

9.4m questions

12.2m answers

Categories