Answer:
Total cost= $4,200
Explanation:
Giving the following information:
It takes 2 finish carpenters 8 days to do the work.
Each finish carpenter ears $37.50 per hour and works 7 hours per day.
To determine the total cost, first, we need to structure the total cost formula:
Total cost= 2*(37.5x)
x= total number of hours
Now, for 8 days:
Total hours= 8*7= 56
Total cost= 2*(37.5*56)
Total cost= $4,200