Which of the following is false? Group of answer choices Lateness in any of the activities located on the critical path would result in lateness in overall project completion time If an activity has a slack value greater than zero, it needs to be a critical activity Lateness in activities, which are not located on the critical path, may or may not result in lateness in overall project completion time, depending on their slack time If there is only one activity in a project, it needs to be a critical activity If Activity A needs to be completed before Activity B starts, Activity A is the immediate predecessor of activity B

1 Answer

3 votes

Answer:

If an activity has a slack value greater than zero, it needs to be a critical activity

Step-by-step explanation:

The false statement in the group of answer choices is If an activity has a slack value greater than zero, it needs to be a critical activity this is because for an activity to be considered a critical activity its slack value has to be equal to zero and not greater than zero,

activities with critical value greater than zero are considered just activities and not critical activities because there is time range given to the activity

User Cedric Druck
by
4.7k points