Answer: 95.7 hours
Step-by-step explanation:
Let's assume that the second unit will require y labor hours.
Learning percentage = 87% = 0.87
For production of two units, the learning percentage will be:
= y/110
We then equate and this will be:
y/110 = 0.87
y = 110 × 0.87
y = 95.7
Therefore, 95.7 hours will be needed to make the second unit