186k views
2 votes
Pert networks use a simple statistical method to determine the most likely task completion times. describe how expected activity times and variances can be computed in a pert network. describe a situation in which a project manager would choose pert for her project.

User Mr Fett
by
5.9k points

1 Answer

3 votes

Answer: Pessimistic time- the optimistic time then divide that number by 6 and square root that number to get the final number.

Step-by-step explanation:

They can be computed by pessimistic time- the optimistic time divide the number by 6 and square root the number gotten to get the final answer

A manager will choose pert for her project due to uncertainties as regards weather, supplies and availability of labour which would all insert variances into her estimated activity upon completion.

User Andrew Bogaevskyi
by
6.2k points