Answer:
$70,000 overapplied
Step-by-step explanation:
Raymond manufacturing expected job No 59 to cost $600,000 of overhead , $1,000,000 materials and $400,000 labour
The actual production cost is $590,000
$1,140,000 worth of materials were used and $440,000 labour cost
The first step is to calculate the overhead rate
= expected overhead /expected cost of labor
= $600,000/$400,000
= 1.5
The overhead applied can be calculated as follows
= overhead rate× real cost of labor
= 1.5 × $440,000
= $660,000
Therefore the over applied or underapplied can be calculated as follows
= $660,000-$590,000
= $70,000
Hence the overapplied is $70,000