Answer:
fraction form: 6 4/5 work days
decimal form: 6.8 work days
Explanation:
- 8 hours work day = 2.5
if you want 17 tons than,
written proportionally: 2.5 / 8 = 17 / x
x represents how many it will take to reach 17 tons
2.5 / 8 = 17 / x :
cross multiply → (2.5) * x = 2.5x and 8 * 17 =136
2.5x = 136
you want to get x alone so divided both sides by 2.5
2.5x / 2.5 = 136 / 2.5
x = 54.4
so you would need 54.4 hours to produce 17 tons
To find how many work days divided the amount of hours by 8 since 1 work day equals 8 hours
54.4 / 8 = 6.8 work days