Answer:
x1 + x2 + x3 + x4 + x5 + x6 + x7
Step-by-step explanation:
Formulating the problem as an LP
Attached below is an AOA diagram and the completion time of each task is indicated in the diagram, The diagram was based on the conditions given for the completion of each task accordingly.
To complete the project as early as possible we will have assume
x1, x2, x3, x4, x5, x6, and x7 to be the times taken to complete each node
hence the earliest time taken to complete the project
= x1 + x2 + x3 + x4 + x5 + x6 + x7
when : x2 - x1 ≥ 3
x3 - x2 ≥ 2
x4 - x2 ≥ 2
x5 - x3 ≥ 3
x6 - x3 ≥ 3
x7 - x5 ≥ 1
x7 - x6 ≥ 1
also : x1, ............ , x7 ≥ 0