Explanation:
Since, Carlos completes the work in 5 hours.
So, in one hour she will do
part
Since, Jenny completes the work in 9 hours.
So, in one hour she will do
part
(Carlos + Jenny)'s one hour work together

Total time taken by Carlos and Jenny together