Answer:
Projects will be run by the functional organization and project managers expedite change control.
Step-by-step explanation:
A project management office or PMO is a department within an organisation that is tasked with maintaining the standard of project management. They also make sure there is economies of repitition in project execution (ensure success of projects is replicated).
In the given scenario if project managers report to the head of a PMO it means that the project management team is independent of the functional organisation.
So the statement - Projects will be run by the functional organization and project managers expedite change control.
Is false.