Complete Question:
What term is used for the amount of time an activity can be delayed without delaying the early start date of any immediately following activities?
Answer:
Free slack.
Step-by-step explanation:
Free slack is a term is used for the amount of time an activity can be delayed without delaying the early start date of any immediately following activities.
Generally, in the execution of a project, when a task is delayed it normally affects the start or finishing time of the other tasks (successors) in a project. The amount of time that is permitted for an activity to be delayed without delaying the early start date of any immediately following (succeeding) activities refers to the free slack or having an adverse effect on entire project.