The standard direct labor cost for producing one unit of product is 5 direct labor hours at a standard rate of pay of $20. Last month, 18000 units were produced and 88000 direct labor hours were actually worked at a total cost of $1584000. The direct labor quantity variance was

1 Answer

2 votes

Answer:

Direct labor time (efficiency) variance= $40,000 favorable

Step-by-step explanation:

Giving the following information:

The standard direct labor cost for producing one unit of product is 5 direct labor hours at a standard rate of pay of $20.

Last month, 18000 units were produced, and 88000 direct labor hours.

To calculate the direct labor quantity variance, we need to use the following formula:

Direct labor time (efficiency) variance= (Standard Quantity - Actual Quantity)*standard rate

Standard quantity= 18,000*5= 90,000

Direct labor time (efficiency) variance= (90,000 - 88,000)*20

Direct labor time (efficiency) variance= $40,000 favorable

User Stenerson
by
8.5k points

Related questions

asked Nov 3, 2018 207k views
Guigui asked Nov 3, 2018
by Guigui
9.1k points
1 answer
5 votes
207k views
1 answer
1 vote
197k views
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.