Answer:
Option (D)
Explanation:
Total hours worked of Monday= 4:45 hours + 5:00 hours = 9:45 hours
Total hours worked of Tuesday= 4:45 hours + 4:45 hours = 9:30 hours
Total hours worked of Wednesday= 4:30 hours + 4:30 hours = 9:00 hours
Total hours worked of Thursday= 4:45 hours + 4:15 hours = 9:00 hours
Total hours worked of Friday= 4:45 hours + 4:15 hours = 9:00 hours
Total hours worked = 9:45 + 9:30 + 9:00 + 9:00 + 9:00
= 46:15 hours
≈ 46 hours 15 minutes
Option (D) will be the answer.