6.2k views
2 votes
Lossing Corporation applies manufacturing overhead to products on the basis of standard machine-hours. Budgeted and actual overhead costs for the most recent month appear below: Original Budget Actual Costs Variable overhead costs: Supplies $ 8,300 $ 8,490 Indirect labor 10,770 10,120 Fixed overhead costs: Supervision 16,110 14,540 Utilities 15,400 15,450 Factory depreciation 58,130 59,650 Total overhead cost $ 108,710 $ 108,250 The company based its original budget on 8,300 machine-hours. The company actually worked 8,260 machine-hours during the month. The standard hours allowed for the actual output of the month totaled 8,190 machine-hours. What was the overall fixed manufacturing overhead volume variance for the month?

User Fbl
by
6.6k points

1 Answer

0 votes

Answer:

$1,188 unfavorable

Step-by-step explanation:

Volume variance = Budgeted fixed overhead cost - Fixed overhead applied to work in process.

$89,640 รท 8,300 machine hours

= $10.8 per machine hours

= $89,640 - ( 8,190 machine hours * $10.8 per machine hours )

= $89,640 - $88,452

= $1,188 unfavorable

User Ikumi
by
5.8k points