Answer:
22 days
Step-by-step explanation:
number of activities : 3 ( A,B,C)
connected via : SS and FF combination. days lag on SS and F = 2
Durations : 5,10 and 3
A and B is connected by SS and there is a 2-day lag on the SS connection, this means that B will start 2 days after A have ended
i.e when T = 0 , B will start : 5 +2 = 7 days and end in 17 days
while B and C is connected by FF and there is also a 2-day lag on the FF connection, this means that C will start after B has ended and end in 2 days
i.e when B ends at 17 days ; C starts = 17 + 2 = 19 DAYS
hence the project will end in 19 + 3 = 22 days ( i.e when C ends )