Answer:
Anola Company
Activity 3 rate under the ABC System is:
$30 per activity
Step-by-step explanation:
a) Data and Calculations:
Cost Pool
Activity Estimated Cost Activity - Activity - Total
Product A Product B Activity
Activity 1 $18,000 300 200 500
Activity 2 $16,000 500 100 600
Activity 3 $27,000 600 300 900
Activity 3 rate = $27,000/900 = $30
b) The activity rate is the product of the estimated cost of the activity divided by the total activity under the activity cost pool.
c) Under ABC costing technique, costs are accumulated and allocated based on the volume of activity. This is to ensure that each cost unit is allocated a cost that measures with the level of activity for the unit. It eliminates arbitrary allocation of costs.