Fuller Manufacturing's cost of goods manufactured for the month ended October 31 is $6,625,000.
Step-by-step explanation:
Prepare a Cost of Goods Manufactured Schedule as follows :
Direct Materials $1,323,600
Direct labor $1,680,000
Total factory overhead $3,544,200
Add Opening Work in process inventory $455,300
Less Closing Work in process inventory ($378,100)