Answer:
the Fixed cost per unit is $3
Step-by-step explanation:
The computation of the fixed cost per unit is shown below:
Total cost per unit = Direct Material cost per unit + Direct labor cost per unit + variable Overhead cost per unit + Fixed cost per unit
$27 = $15 + $7 + $2 + Fixed cost per unit
$27 = $24 + Fixed cost per unit
So,
Fixed cost per unit is
= $27 - $24
= $3
hence, the Fixed cost per unit is $3