Answer:
c. The project is meeting its expected completion date but a certain activity/ event on that path is not meeting its expected completion date.
Step-by-step explanation:
- Float is the total amount of a project delay. A negative float means a delay longer than the intended or allowed float at a given time. This means that a float is an activity that takes longer than initially thought.
- Some projects have built-in standard floats, which are calculated based on previous experience of similar projects, with allowances given for some different expected backstory.