Answer:
Negative Float on a Partial Path:
c. The project is meeting its expected completion date but a certain activity/ event on that path is not meeting its expected completion date.
Step-by-step explanation:
Float is the quantification of delays in a project. Negative float means that there is a delay exceeding the intended or allowed float by an ascertainable time. This means that float is about the time when an activity takes longer than originally planned. Some projects have inbuilt standard float which had been computed based on past experience of similar projects, with some allowances made for different expected scenarios.