Answer:
Analyze the variance
Step-by-step explanation:
In a situation like this, it is expected that the project manager identifies the differences or variance which exists between the baseline scope and actual project performance. It is however when the variance has been analyzed, then the project manager can conclude whether a change in scope is needed or not.
Hence, in this case, what Monica need to do next is to ANALYSE THE VARIANCE