Answer:
a. $3.00
Step-by-step explanation:
Calculation of activity rate for activity 1
Activity rate = Budgeted cost of activity 1/Total budgeted activity
=$87,000 / (3,000 + 2,800)
=$87,000/5,800
=$15
Calculation of activity rate for activity 2.
Activity rate = Budgeted cost of activity 2 /Total budgeted activity
=$62,000 / (4,500+5,500)
=$62,000 / 10,000
=$6.20
Calculation of activity rate for activity 3
Activity rate = Budgeted cost of activity 3 / Total budgeted activity
=$93,000 / (2,500+5,250)
=$93,000 / 7,750
=$12
Calculation of total overhead cost of product A.
Total overhead cost = Activity1 + Activity2 + Activity3
Total overhead cost = (3,000×$15) + (4,500×$6.20) + (2,500×$12)
Total overhead cost = $45,000+$27,900+$30,000
Total overhead cost = $102,900
Thus, the total overhead cost allocated to product A is $102,900.
Calculation of overhead cost per unit.
Overhead cost per unit = Total overhead cost allocated / Number of units produced
= $102,900 / 34,300
= $3 per unit
Thus, the overhead cost per unit of product A is $3