Answer:
Cost allocated to land=$605,520
Cost allocated to building=$1,482,480
Step-by-step explanation:
Calculation for the amount that Schwartzkopf should report the land and the building at the end of the year
A. Calculation for Cost allocated to land
Using this formula
Cost allocated to land=Fair value of land/
Fair value of building and land×Cost
Let plug in the formula
Cost allocated to land=$826,355/($2,023,145+$826,355)×$2,088,000
Cost allocated to land=$826,355/$2,849,500×$2,088,000
Cost allocated to land=0.29×$2,088,000
Cost allocated to land=$605,520
Therefore the Cost allocated to land will be $605,520
B. Calculation for Cost allocated to building
Using this formula
Cost allocated to building=Fair value of land/
Fair value of building and land×Cost
Let plug in the formula
Cost allocated to building=$2,023,145/$2,023,145+$826,355)×$2,088,000
Cost allocated to building=$2,023,145/$2,849,500×$2,088,000
Cost allocated to building=0.71×$2,088,000
Cost allocated to building=$1,482,480
Therefore Cost allocated to building will be $1,482,480