Estimated costs for activity cost pools and other item(s) are as follows: Machining $500000 Assembling 160000 Advertising 450000 Inspecting and testing 135000 Total estimated overhead is

User Joedragons
by
4.0k points

1 Answer

6 votes

Answer:

Total estimated overhead is $1,245,000.

Step-by-step explanation:

Calculation of Estimated Overhead :

Machining $500,000

Assembling $160,000

Advertising $450,000

Inspecting and testing $135,000

Total Overhead $1,245,000