A Work Breakdown Structure (WBS) identifies deliverables, activities, and tasks. Which statement describes a task? Work performed to complete or manage the deliverables for a project Discrete work required to complete parts of a project Tangible and measurable outcome expected from a project A list that identifies the logical way to progress through work

1 Answer

4 votes

Answer:

The correct option is;

Work performed to complete or manage the deliverables for a project

Step-by-step explanation:

In other to manage project tasks, and make them easier to perform and approachable, it is a common methodology to split the entire tasks into smaller units that are easily managed

Work Breakdown Structure (WBS) is a project tool that is used to sort the project goal into smaller required activities, deliverables and tasks of the project

Project task is the work unit that brings about progress or advancement of the aims of the project that has a due date for completion.