Answer:
$880 favorable
Explanation:
The computation of direct materials price variance for last month is shown below:-
Direct material price variance = Actual quantity × (Standard price - Actual price)
= 2,200 × ($8 - ($16,720 ÷ 2,200)
= 2,200 × ($8 - 7.6)
= 2,200 × $0.4
= $880 Favorable
Therefore for computing the direct materials price variance for last month we simply applied the above formula.