Answer:
$1.8 Unfavourable
Step-by-step explanation:
Labor usage variance can be calculated by deducting Standard hours from Actual hours and multiplying the result by the standard rate.
DATA
Standard hours = 1.50 hours
Standard rate = $12/hour
Actual hours = 1.65 hours
Actual rate = $11.5/hour
Calculation
LABOUR USAGE VARIANCE = (SH-AH)SR
LABOUR USAGE VARIANCE =(1.5 - 1.65) x $12
LABOUR USAGE VARIANCE = (-0.15) x $12
LABOUR USAGE VARIANCE = $1.8 Unfavourable