Answer: $2,585
Step-by-step explanation:
Total budgeted amount for direct labor;
Production is estimated at 470 boxes.
Each box requires 0.5 hours of direct labor
Employees are paid $11 per hour.
= 470 * 0.5 * 11
= $2,585