Answer:
a. $1,700 U
b. $3,260 F
Step-by-step explanation:
a. Fixed over head budget variance = Actual fixed overhead - Budgeted fixed overhead
Actual fixed overhead = $35,700
Budgeted fixed overhead = $34,000
Fixed overhead budget variance = $35,700 - $34,000
= $1,700 U
b. Fixed overhead volume variance = Budgeted fixed overhead - Standard fixed overhead
Standard fixed overhead application rate = $2 per machine hr × 1hr
= $2
Budgeted fixed overhead = $34,000
Standard fixed overhead = Standard hours for actual output × Budgeted rate
= (18,630 units × 1hr) × $2
= $37,260
Fixed overhead volume variance
= $34,000 - $37,260
= 3,260 F