145k views
2 votes
Lopez Company uses both standards and budgets. For the year, estimated production of Product X is 500,000 units. Total estimated cost for materials and labor are $1,400,000 and $1,700,000.

Compute the estimates for (a) a standard cost and (b) a budgeted cost. (Round standard costs to 2 decimal places, e.g. 1.25.)

1 Answer

4 votes

Answer:

a. Standard cost = Total estimated cost of material รท Estimated production

= $1,400,000 / 500,000 unit

= $2.80 per unit

Thus, the standard cost of material is $2.80, and the budgeted cost is $1,400,000.

b. Standard cost = Total estimated cost of labor / Estimated production

= $1,700,000 / 500,000

= $3.40 per unit

Thus, standard cost of labor is $3.40 and budgeted cost is $1,700,000.

User RobinAugy
by
5.9k points