Answer:
Variable manufacturing overhead rate variance= $4,596 unfavorable
Step-by-step explanation:
Giving the following information:
Variable manufacturing overhead 0.50 hours $8.80 per hour $4.40
Actual direct labor hours= 1,200
Variable manufacturing overhead costs during March totaled $15,161.
To calculate the variable overhead rate variance, we need to use the following formula:
Variable manufacturing overhead rate variance= (standard rate - actual rate)* actual quantity
Actual rate= 15,161/1,200= $12.63
Variable manufacturing overhead rate variance= (8.8 - 12.63)*1,200
Variable manufacturing overhead rate variance= $4,596 unfavorable