Answer:
d. Our workforce may be waiting on delayed arrivals of inputs needed to do the work.
Step-by-step explanation:
There are two possible sources for 25% of the jobs not being delivered on time:
- we have a problem with inputs required (materials or labor)
- we have a problem with the capacity of our facility
If we followed Juran's Law, we can simply assume that the problem here has to do with our productive system (like 85% of production errors). Two clear problems are obvious:
- only 380 hours worked out of total of 480 hours per week ⇒ why didn't anyone work during the remaining 100 hours? Is there a delay with the inputs or we don't have enough workers?
- only 85% of the facility's capacity is being used ⇒ why only 85% of the effective capacity ratio? If we are finishing jobs late, why do we have 15% of unused capacity?
Obviously we cannot answer these questions just be reading two paragraphs, but that is what should be answered in order to solve the issues.