Answer:
Machine= 736,000
Installation= 92,000
Training= 92,000
Step-by-step explanation:
Giving the following information:
The machine, installation, and training typically cost $800,000 $100,000, and $100,000 respectively when each is provided in a separate contract.
Shaw and Maya agree to a total contract price of $920,000.
First, we need to determine the proportion of each:
Machine= 800,000/1,000,000= 0.8
Installation= 100,000/1,000,000= 0.1
Training= 100,000/1,000,000= 0.1
Now, we can allocate:
Machine= 0.8*920,000= 736,000
Installation= 0.1*920,000= 92,000
Training= 0.1*920,000= 92,000