250,857 views
37 votes
37 votes
In the EST graph above, what is the required time to complete task A? ​

In the EST graph above, what is the required time to complete task A? ​-example-1
User Oziomajnr
by
2.5k points

1 Answer

12 votes
12 votes

Answer:

5 time units

Explanation:

The number on the arrow in this graph is the task completion time.

__

The completion time for Task A is 5 time units.

In the EST graph above, what is the required time to complete task A? ​-example-1
User Wobsta
by
2.8k points