Answer:
8 time periods
Explanation:
This Earliest Start Time graph shows task completion times on the arrow out of the bubble representing the task.
__
Task E completes in 8 time periods.
_____
Additional comment
The number in parentheses inside the bubble is the number of time periods before the task can be started, at the earliest. That number in the Finish bubble is the earliest the project can be completed.