Trendy Coats is looking at financials to prepare end of year reports. Actual hours used were 4,000. Standard hours allowed were 5,000. Actual wage paid per hour was $13. The total labor flexible budget variance was ($23,000) Favorable. What was Trendy Coat’s standard price? Select one: a. $15.00 b. $12.00 c. $17.00 d. $13.50

User Salvob
by
5.8k points

1 Answer

1 vote

Answer

a) $15

Step-by-step explanation:

We will use the formula for Total labor variance to arrive at Standard rate.

Total labor variance = (Actual hours × Actual rate) - (Standard hours × Standard rate)

Substituting the data above into the formula, we'll have;

-$23,000 = (4,000 × $13) - (5,000 × SR)

-$23,000 = $52,000 - 5,000SR

Collect like terms

5,000SR = $52,000 + $23,000

5,000SR = $75,000

SR = $75,000 / 5,000

SR = $15