Answer:
80 hours for 2 workers to build 8 cars
Explanation:
2 cars / 8w *5 hr = 2 cars / 40 hrs 1 car takes 20 hrs
8 cars * 20 hours = 160 hours required
two workers split this time 160/2 = 80 hours