Answer:
$86,000 and $99,380
Step-by-step explanation:
The flexible budget formular is fixed at $50,000 plus variable costs
The direct labor hour is $4 per hour
The total budgeted cost at 9,000 hours can be calculated as follows
= $50,000 + ($4×9,000 hours)
= $50,000 + $36,000
= $86,000
The total budgeted cost at 12,345 hours can be calculated as follows
= $50,000 + ( $4×12,345 hours)
= $50,000 + $49,380
= $99,380
Hence the total budgeted cost at 9,000 hours and 12,345 hours is $86,000 and $99,380 respectively