Answer:
Re-order quantity = 256.6 or 257 units
Step-by-step explanation:
We can calculate the reorder point for the company at 99% service level as follows
Solution
The Standard deviation of demand during lead time = sigma
Average daily demand = d
lead time = L
Standard deviation covered 99% = Z
DATA
Sigma =20 units
d= 30 units per day
L= 7 days
Z= 2.3
Calculation
Reorder quantity = (d x L) + (Z x sigma)
Reorder quantity = (30x7) + (2.33 x 20)
Reorder quantity = 210 + 46.6
Reorder quantity = 256.6 or 257 units