Answer:
Flexible budget cost formula for indirect labor is $0.25 per DL hours
Step-by-step explanation:
Flexible budget cost for indirect labor = Actual indirect labor cost + Associated spending variance
= $5,780 + $245
= $6,025
Flexible budget cost formula for indirect labor= Flexible budget cost for indirect labor / Direct labor-hours
= $6,025 / 24,100 DL hours
= $0.25 per DL hours