Answer: True
Step-by-step explanation:
The range of feasibility is used to measure values that are on the right-hand-side(objective function) that won't alter dual prices.
When the range of feasibility indicates that the original amount of a resource, which was 20, can increase by 5, then the amount of the resource can increase to (20 + 5) = 25
Therefore, the option is true