Answer:
the labor efficiency variance for the month is $23,256 Favorable.
Step-by-step explanation:
Labor efficiency variance = (Aq × SP) - (Sq × Sp)
= (7,600 × $13.60) - ((950 × 9.8) × $13.60)
= (7,600 × $13.60) - (9.310 × $13.60)
= $23,256 Favorable