The following data is given for the Bahia Company: Budgeted production 1,049 units Actual production 971 units Materials: Standard price per pound $1.971 Standard pounds per completed unit 12 Actual pounds purchased and used in production 11,302 Actual price paid for materials $23,169 Labor: Standard hourly labor rate $15.00 per hour Standard hours allowed per completed unit 4.3 Actual labor hours worked 5,000.65 Actual total labor costs $76,260 Overhead: Actual and budgeted fixed overhead $1,014,000 Standard variable overhead rate $27.00 per standard labor hour Actual variable overhead costs $140,018 Overhead is applied on standard labor hours. The variable factory overhead controllable variance is a.$75,397.52 unfavorable b.$75,397.52 favorable c.$27,284.90 unfavorable d.$27,284.90 favorable

User Joppiesaus
by
7.5k points

1 Answer

6 votes

Answer:

c.$27,284.90 unfavorable

Step-by-step explanation:

Standard variable overhead rate =$27.00

Standard hours allowed per completed unit =4.3

Actual production unit =971

Actual variable overhead costs =$140,018

Variable factory overhead controllable variance = (Standard variable overhead rate * Standard hours allowed per completed unit * Actual production unit) - Actual variable overhead costs

Variable factory overhead controllable variance = ($27 * 4.3 * 971) - $140,018

Variable factory overhead controllable variance = $112,733.1 - $140,018

Variable factory overhead controllable variance = $27,284.9 (Unfavorable)