Answer:
$1,000 unfavorable and $224 unfavorable
Step-by-step explanation:
The computation of the direct material quantity variance and the direct labor time variance is shown below:
For direct material quantity variance:
= (Standard direct materials ÷ bugeted toy × actually produced) - actual direct materials
= ($36,000 ÷ $24,000 × 21,600 units) - $33,400
= $32,400 - $33,400
= $1,000 unfavorable
For direct labor time variance
= (Standard direct labor ÷ bugeted toy × actually produced) - actual direct labor
= ($8,640 ÷ $24,000 × 21,600 units) - $8,000
= $7,776 - $8,000
= $224 unfavorable