Answer:
Step-by-step explanation:
Standard pounds per cake = 3 pounds
Standard unit price = $3
Standard pounds 5500 cakes = 16,500 pounds
Actual pounds per 5500 cakes = 16,650
Variance = (16,650 - 16,500)=150
Cost of actual materials used = actual materials * standard price
=16,650*3 =49,950
Cost of work in progress = Standard materials * standard price = 16,500*3= 49.500
Direct material quantity variance = Quantity variance * 3
150*3 = 450
Journal entry
Debit work in progress = 49,500
Debit material quantity variance = 450
Credit Material = 49,950